FOI request (FOIR-250659746)
EV chargers
Requested Thu 17 September 2020
Responded Mon 28 September 2020I would be grateful if you could please provide the following information via email under the Freedom of Information Act:
1. How many EV charging points have you installed in your authority area since 2017? (Please give data broken down by calendar year)
2. How many EV charging points that are currently installed in your authority area are either a) rapid 43kW+, b) fast 7kW-42kW or c) slow 3kW-6kW? (Please give data separately, as of today's date)
3. How many EV charging points do you plan to install in your authority area between today's date and 31st December 2025 that are either a) rapid 43kW+, b) fast 7kW-42kW or c) slow 3kW-6kW? (Please give data separately broken down by calendar year - if 2025 is too far away, please give details on as much forecast as you have)
4. How many requests lobbying for on-street EV charging points have you received since 2017? (Please give data broken down by calendar year)
Please prioritise your response to the questions in the order asked i.e. if time constraints do not allow for all questions to be answered, please answer Q1 first.
Response
Q1 and Q2
2020 - 2x 7kW and 2x 22kW
2019 - Nil
2018 - 1x 7kW
2017 - Nil
Q3 - Unknown up to 2025. We are hoping to install a further 14x 22kw units before April 2021.
Q4 - Information not held - on street parking is dealt with by East Sussex County Council, please visit their website for further information: https://www.eastsussex.gov.uk
-
-