-
Buckshole reservoir safety works
Buckshole reservoir safety improvement works 2021
The three reservoirs within Alexandra Park were built in Victorian times to supply water to Hastings. Buckshole Reservoir, the largest of the three and the last to be built is now more than 150 years old.
The reservoirs no longer supply drinking water, but they are still an asset to the town, providing a focus for fishing, recreation and wildlife.
Why are these improvements being made?
We continue to maintain our reservoirs to the highest safety standards in line with current regulations. A detailed inspection of the reservoirs in 2016 identified the need for improvement works at Shornden and Buckshole Reservoirs. The works at Shornden Reservoir were completed in 2018. For Buckshole Reservoir further investigations and studies have been needed to determine the scope of work required to help ensure the integrity of this important part of the park for the future.
The safety standards required for large bodies of impounded water have been raised over the years. The recommendations for improvement work from the 2016 inspection have been made with reference to current standards.
What exactly is being done?
During the time since the recommendations for the improvement work were made, a number of studies have been carried out to help identify the most appropriate course of action to meet current standards within the setting of Alexandra Park. As well as the engineering requirements, ecology, landscape and heritage studies have been commissioned to help ensure the proposed works are carried out in the most sympathetic way, avoiding adverse impacts.
The proposed improvement works are:
- A new outlet pipe, to be built within the existing overflow structure, which will allow the reservoir to be drained in a timely manner should a problem with the dam ever be detected.
- A new spillway channel to replace the original and aged structure which has now deteriorated beyond economic repair. The new channel will be larger than the original to ensure it can cope with and protect the dam from the largest predicted floods.
When are these works being done?
A planning application for the proposed works is due to be submitted in the autumn of 2020, subject to completion of supporting studies and reports. This should allow preparatory works to start during the early part of 2021, with the main construction activities due to be on site during summer 2021. The works should be complete by early 2022.
Will there be an impact on the environment and residents?
Protecting the environment and maintaining the amenity value of the lakes for the enjoyment of our community are very important to us. An ecology assessment has been undertaken to ensure negative impacts are avoided and discussions are taking place with Historic England regarding the heritage interest of the park.
During construction, planned for summer 2021, it will be necessary to temporarily close-off access to the area around the western side of the dam so that the work can be carried out safely.
We also realise that noise can be an issue during construction, and this will be addressed by careful selection of an experienced contractor and the use of appropriate construction machinery and equipment.
-
Hastings' parks
Actions
Contact
Got a question about parks and gardens?
Comments
The content on this page is the responsibility of our Parks and Gardens team.